Road Development Agency (RDA) Director Communications and Corporate Affairs Masuzyo Ndhlovu who is on a media tour of various road projects in Muchinga and Northern Provinces is impressed with the progress so far recorded on the Chinsali-Nakonde road. 

Lot 1 which is a 103 km stretch from Chinsali to Isoka and being worked on by China State Construction Engineering Limited has recorded 27.92 percent physical progress. 

Lot 2 has a stretch of 107 km, from Isoka to Nakonde and the contractor is China Railway Seventh Group Company Limited. Physical progress on this Lot stands at 25.57 percent. 

The consultant on both Lots is Civil and Planning Group.